Thanks!
I am lucky enough to have a brother in law that's an electrician so I subbed that out. I built the panel and mounted everything. Left the dangerous stuff to him. All it cost me was a red dot scope for his AR-15! He will be down on Sunday to wire up my spa panel. I should have a ton of updates this weekend. Here is my to-do list.
Finish up control panel mount
Mount control panel to mount
Build the hoses for the brewery
Mount the thermocouples in the kettle and HLT
Complete the kegerator. (Build of that is in the sig)
Wash all of my beer glasses and place them in new cabinet
I also bought two 4ft work lights. I am going to replace the single 60w bulb with two 4ft lights. Should really brighten the area up.
She is working all weekend so I have a lot of time to fiddle around in the garage. I'll start some stuff tonight, work all day tomorrow and most of the day Sunday if I need to. I should probably get most of it done tomorrow.
If all goes right. I should have a functioning brewery by the end of the weekend. Then I'll have to see what I can do for ventilation. Pretty sure she won't be too pleased with giant hood. Can probably just get away with opening the garage door.
Br1dge, good luck with your build. Do you have a thread started?