I have gone thru at least 5 different systems over the past couple years and never really documented the build. I thought I would this time. It won't be all that different for others, just a combination of many, but hopefully someone will get something out of it. It's the least I can do for the community as I have gain much knowledge from this site.
I will be using the following in the design:
1 HLT HERMS SS Keggle
1 BK SS Keggle
1 Mashtun Insulated SS Keggle
1.5x1.5x14 gauge mild steel
60K BTU LP 10" Burners
Standing Pilot Gas Valves
PID Temperature Controllers
I would like to use this post like a journal, so I will be posting as much as I can about the build to document progress, drawing, price lists, vendors, etc...
I have a budget $1500.00 for everything but the mashtun and pumps as I already have them in my current system.
That being said here is my current stand alone eHerms system to get things started:
FULL SYSTEM
eHERMS and Controller
eHERMS coil and element
I will be using the following in the design:
1 HLT HERMS SS Keggle
1 BK SS Keggle
1 Mashtun Insulated SS Keggle
1.5x1.5x14 gauge mild steel
60K BTU LP 10" Burners
Standing Pilot Gas Valves
PID Temperature Controllers
I would like to use this post like a journal, so I will be posting as much as I can about the build to document progress, drawing, price lists, vendors, etc...
I have a budget $1500.00 for everything but the mashtun and pumps as I already have them in my current system.
That being said here is my current stand alone eHerms system to get things started:
FULL SYSTEM
eHERMS and Controller
eHERMS coil and element