It's done. That's a huge healthy pitch of 1028. It works fast. I've had a stout reach FG in 3 days with it.
Bottle/keg you're good to go.
I never do the repeated gravity readings 3 days apart etc. I find with all my batches once they stop bubbling and clear they are done. Nothing changes after that. A nice healthy pitch rate with controlled fermentation will eliminate any off-flavors associated with poor yeast husbandry.
Yeast do clean up unwanted stuff but with gravities of the beers I make (less than 1.060) that is a fast process, typically 24-48 hours if the experts are to be believed.
2 weeks is a solid time frame for most ales. Good to package.
Recent different example
Got a lager on the go now in my chamber and with it being a lager and the ferment profile I am following, a gravity reading yesterday was appropriate. 1.048 OG. Measured yesterday at 1.014 6 days after pitching yeast and a fermentation at 50F. It's still going and will drop more as I ramp it up.
Packaging in a week or so I would imagine once I'm sure it's finished. Then it will lager as needed.