This really looks like an exciting project. (At least for me.) I have a lot of ideas spinning in my head. The possibilities are ... Nevermind.
Getting old sucks.!
Getting old sucks.!
P-J said:This really looks like an exciting project. (At least for me.) I have a lot of ideas spinning in my head. The possibilities are ... Nevermind.
Getting old sucks.!
Thank you for that. Yea, I tend to think outside the box and then spend lots of time trying to explain my thinking.Not old, experienced and that results in lots of ideas/ways to get things done, right?
I recently converted a 15 year BrewMagic to electric. Still using propane for the boil kettle burner. I swapped the old jet burner with a Banjo burner.
![]()
I really hated the fact that Sabco used all stainless on the visible plumbing but the heater chamber was copper. This really limited the the chemicals I could use to clean the system. I also didn't like the fact that the chamber was hard to take apart and clean. I remember some interesting stuff coming out of the chamber after along time of not using it.
The sight glass is to check clarity and also to make sure I don't have any air in the heating chamber.
While I was at it I added some inverted kegs to allow bottom drain, and also had a bunch of fun with valves, stainless tubing and other stuff! I guess the only thing left from the original system was the stand!
![]()
Replacing the element is a good idea, or at least pulling it out to see what condition it is in. Here is what mine looked like after a year+ of sitting:
![]()
The chamber does not allow for easy cleaning, and it tends to trap gain. It also does not drain well, at least my generation system didn't.
I would recommend using the PID to control the boil.Is a PID necessary to control the element in the boil kettle? Is there any other option to control the power output to the heating element, maybe something as simple as a dial? The dial would probably require wiring a board in the same manner I did to control the fan speed in my stir plate and might end up costing more than a PID...
I'm looking at over $350 for just the three additional PID, 4 SSRs, 4 contactors, and 4 heat sinks...just trying to keep this somewhat under control.![]()
I would recommend using the PID to control the boil.
Please let me come up with another plan for you that will be far less expensive to put together. Just a couple of days should get it there.
Do you intend to use the RIMS setup or will you be using a HERMS coil setup?
You have the concept on the HERMS set up. All you need is a 25' or 50' coil of 1/2" OD copper and a few fittings to make a really nice HERMS coil.I don't know much about HERMS. Something along the lines of pumping the wort through a heat exchanger that's usually submerged in the HLT (which is set to a temp equal to or slightly above the desired mash temp) and then returned to the top of the mash.
I know how RIMS works. I'll probably RIMS since that's what's on the system now and if I need to rebuild the existing RIMS tube, I can probably do that cheaper than a HERMS setup.
You have the concept on the HERMS set up. All you need is a 25' or 50' coil of 1/2" OD copper and a few fittings to make a really nice HERMS coil.
1/2" OD X 25FT - REF $27.64
1/2" OD X 50FT - REF $54.53
Now regarding the RIMS. Your IF is something to think about. Rebuild as in replace the element? Yes it would be cheaper depending on the actual element you choose to fire it (the choices are many and you really need to choose the correct one). Then you have to decide if you want a seperate PID to control it. Most cases and setups would require a PID just for the RIMS otherwise it can get tricky with the balance of your brew process. The other possible part of the IF is if you end up replacing the RIMS tube. With that, the cost goes through the roof.
Your setup can be done for a lot less money than what it would be with my first (more to come) diagram. You can use a single PID for a HERMS setup. It can also be done with a single PID with RIMS but you would have to overlord the system and manage it through every step. 2 PIDS with RIMS would be very doable and easier to manage.
I'd be please to help you down any path that you choose to go. No problem.!
P-J