Hers the lastest update on my pump control box. All the wires have been run; 2x 120v loads (one controlled by the mash temp PID). I also have 3x 120v out lines (one for each pump) On my HERMS pump, I have installed a selector switch to allow me to switch that pump on by hand.
The big black box in there is a 24vac transformer which steps down my 120v load to run my 24v water solenoids. Each solenoid has an autofill switch on my control box, each line will have a float switch interrupter to close the solenoid when the pot has filled to whatever volume I desire.


The only potential issue I foresee is overheating...however; I don't see that transformer really getting so hot that anything would melt. Let me know if you think otherwise
The big black box in there is a 24vac transformer which steps down my 120v load to run my 24v water solenoids. Each solenoid has an autofill switch on my control box, each line will have a float switch interrupter to close the solenoid when the pot has filled to whatever volume I desire.


The only potential issue I foresee is overheating...however; I don't see that transformer really getting so hot that anything would melt. Let me know if you think otherwise