So after about 6 months i am very close to finishing my man cave/ brewing room. When i started working on the room all i had was sheetrock on the walls. I went with acid staining the cement for easy clean out. I went with conventional cabinets and granite in case a ever get out of brewing and just want to use the area as a bar ( however that is very unlikely)
I ordered my panel from Ryan @ ebrewsupppy. I am still learning to use the BCS 460. He did a great job on the panel for a very reasonable cost.
I need to hook up my ventilation system and test run everything still, but i am sure the ventilation system will work fine. I think i can just open the window a little bit and get all the make up air a need.
I mounted the pumps and chiller on a roll up drawer under the cabinet. Thats the best i could come up with at this time. I am open to suggestions on that.
If anyone has any input i am open to suggestions.
Thanks
I ordered my panel from Ryan @ ebrewsupppy. I am still learning to use the BCS 460. He did a great job on the panel for a very reasonable cost.
I need to hook up my ventilation system and test run everything still, but i am sure the ventilation system will work fine. I think i can just open the window a little bit and get all the make up air a need.
I mounted the pumps and chiller on a roll up drawer under the cabinet. Thats the best i could come up with at this time. I am open to suggestions on that.
If anyone has any input i am open to suggestions.