Hi everybody!
I am brewing 1.045 - 1.055 ales which usually reach terminal gravity on day 3-4 and I keep wondering if keeping the beer in the fermenter a lot longer than that is necessary.
I've been listening to interviews some professional brewers have given, paying special attention to their fermentation regime.
A brewer describing their award winner 4.7% pale ale described it roughly as: monitor fermentation until 1/2 plato above terminal, this happens in 3 days, add dry hops and keep them in for 3-4 days after which, if the beer passes diacetil test, the hops/yeast is dumped and the beer conditioned cold (I assume for stability) prior packaging.
Stating the obvious, it appears to me that in professional brewing, when the beer is ready, the beer is packaged and sold. How this compares to homebrewing, where to the best of my knowledge, we rarely take less than 2 weeks to package?
For example, lets say I make 1.050 wort for non-dry hopped beer, start fermentation at 17C and set my controller to cap the rising temperature to 20C. When the beer reaches FG (or it is very close to), up the temperature to 22C for 24 hours. In my limited experience, all this may take about 4-5 days. That means that I could be packaging 7 days after pitching, including 2 days of cold crashing. Assumed fast fermenting flocculant healthy yeast (such as WLP002 or WLP007), proper levels of oxygen and knowledge where the FG is meant to end up.
Thanks!
I am brewing 1.045 - 1.055 ales which usually reach terminal gravity on day 3-4 and I keep wondering if keeping the beer in the fermenter a lot longer than that is necessary.
I've been listening to interviews some professional brewers have given, paying special attention to their fermentation regime.
A brewer describing their award winner 4.7% pale ale described it roughly as: monitor fermentation until 1/2 plato above terminal, this happens in 3 days, add dry hops and keep them in for 3-4 days after which, if the beer passes diacetil test, the hops/yeast is dumped and the beer conditioned cold (I assume for stability) prior packaging.
Stating the obvious, it appears to me that in professional brewing, when the beer is ready, the beer is packaged and sold. How this compares to homebrewing, where to the best of my knowledge, we rarely take less than 2 weeks to package?
For example, lets say I make 1.050 wort for non-dry hopped beer, start fermentation at 17C and set my controller to cap the rising temperature to 20C. When the beer reaches FG (or it is very close to), up the temperature to 22C for 24 hours. In my limited experience, all this may take about 4-5 days. That means that I could be packaging 7 days after pitching, including 2 days of cold crashing. Assumed fast fermenting flocculant healthy yeast (such as WLP002 or WLP007), proper levels of oxygen and knowledge where the FG is meant to end up.
Thanks!