Default Brewery Wiring Diagram, I need your thoughts!

Ok, here is what I had a chance to sketch up this morning. I want to preface this by saying that I am not an electrician and I plan on having an electrician review my work before anything is turned on/plugged in or used.

The Neutral Bus, 3 pole distribution block, SPST's, DPST's and SSR's will all be housed in a junction box. The pumps and kettles will plug into the control box via L6-30 (elements) and L5-15 (pumps) twist lock receptacles and plugs. These are not in the diagram, but will be soon.

The control box will plug into the 14-50 receptacle via a 14-50 plug. And the 14-50 receptacle will be wired to the 50A GFCI breaker. I opted against separate breakers for the elements and 110 stuff because this will be connected less than 10 feet from my load center and the added cost didn't seem needed to save walking an extra 4 feet to kill power if needed. If anyone can provide a compelling argument against this I will more than consider it.

So far everything has been purchased except the junction box and the GFCI breaker. Still holding out to find a decent deal on those.

Thoughts?

__________________
Primary: Cherry Vanilla Melomel, Blueberry melomel, Orange Cranberry Melomel, Port, Orange Blossom Muscat, Dubbel, Golden Strong

Secondary: 9/9/9/-My version, Carbernet Sauvignon, Merlot, Raspberry Melomel

On deck: Tripel, 5 day IPA Squared, White Russian Imperial Stout

Live in Saint Louis, MO? Then check out www.stlbrews.org and www.garagebrewers.com
HarvInSTL is offline
 
Reply With Quote Quick reply to this message
Old 03-27-2009, 07:26 PM   #2
Gussymo
HBT_LIFETIMESUPPORTER.png
Feedback Score: 0 reviews
 
Gussymo's Avatar
Recipes 
 
Join Date: Feb 2008
Location: Lodi
Posts: 166
Liked 1 Times on 1 Posts
Likes Given: 3

Default

Are youe using the Auber PID's?

__________________
Gussymo is offline
 
Reply With Quote Quick reply to this message
Old 03-27-2009, 07:31 PM   #3
Gussymo
HBT_LIFETIMESUPPORTER.png
Feedback Score: 0 reviews
 
Gussymo's Avatar
Recipes 
 
Join Date: Feb 2008
Location: Lodi
Posts: 166
Liked 1 Times on 1 Posts
Likes Given: 3

Default

The reason I asked if it was Auber is because I have mine powered with
120v. They may work on 220v. I'd have to look at the specs. If you use 120v to power the PID, you will need one hot and the neutral to the PID.

__________________
Gussymo is offline
 
Reply With Quote Quick reply to this message
Old 03-27-2009, 07:37 PM   #4
HarvInSTL
Feedback Score: 0 reviews
 
HarvInSTL's Avatar
Recipes 
 
Join Date: Apr 2007
Location: Saint Louis, MO
Posts: 739
Liked 2 Times on 2 Posts
Likes Given: 1

Default

No, I am using the BCS-460. It arrived a few weeks ago, I've just been slacking on getting this ebrewery built. Since I sold my brutus rig, the heat is on to get this ebrewery up and running.

__________________
Primary: Cherry Vanilla Melomel, Blueberry melomel, Orange Cranberry Melomel, Port, Orange Blossom Muscat, Dubbel, Golden Strong

Secondary: 9/9/9/-My version, Carbernet Sauvignon, Merlot, Raspberry Melomel

On deck: Tripel, 5 day IPA Squared, White Russian Imperial Stout

Live in Saint Louis, MO? Then check out www.stlbrews.org and www.garagebrewers.com
HarvInSTL is offline
 
Reply With Quote Quick reply to this message
Old 03-27-2009, 07:55 PM   #5
Gussymo
HBT_LIFETIMESUPPORTER.png
Feedback Score: 0 reviews
 
Gussymo's Avatar
Recipes 
 
Join Date: Feb 2008
Location: Lodi
Posts: 166
Liked 1 Times on 1 Posts
Likes Given: 3

Default

I see. That looks pretty slick. Good luck with that.

__________________
Gussymo is offline
 
Reply With Quote Quick reply to this message
Old 03-29-2009, 06:50 PM   #6
HarvInSTL
Feedback Score: 0 reviews
 
HarvInSTL's Avatar
Recipes 
 
Join Date: Apr 2007
Location: Saint Louis, MO
Posts: 739
Liked 2 Times on 2 Posts
Likes Given: 1

Default

Any other thoughts?

__________________
Primary: Cherry Vanilla Melomel, Blueberry melomel, Orange Cranberry Melomel, Port, Orange Blossom Muscat, Dubbel, Golden Strong

Secondary: 9/9/9/-My version, Carbernet Sauvignon, Merlot, Raspberry Melomel

On deck: Tripel, 5 day IPA Squared, White Russian Imperial Stout

Live in Saint Louis, MO? Then check out www.stlbrews.org and www.garagebrewers.com
HarvInSTL is offline
 
Reply With Quote Quick reply to this message
Old 03-29-2009, 08:56 PM   #7
tipicreeper
Feedback Score: 0 reviews
Recipes 
 
Join Date: Dec 2008
Location: Arizona
Posts: 192
Liked 2 Times on 1 Posts

Default

First off. Good luck with your build.
Next, you should add some down stream fusing to protect the wire gauge size and also the down stream componants.
For instance; appropiate sized fuses for each of your pumps and sized fuses for your heating elements. Essentially to protect against a catastophic failure. (a heating element was to burn out and fuse to ground or a pump winding was to fail) This will also allow you to drop wire gauge sizes in each of the branch circuits.
According to your diagram there is no branch fusing until the 50A breaker so the wire gauge size through out would be required to handle 50A before the jacket melts. That's some heavy gauge wire.
Also, I'm not seeing any controllers to control the SSR's. I would also fuse those with fast blow fuses.
Just my opinion,
If I can help in any way, please let me know.
Cheers
-David

__________________
tipicreeper is offline
 
Reply With Quote Quick reply to this message
Old 03-29-2009, 09:20 PM   #8
AiredAle
Feedback Score: 0 reviews
Recipes 
 
Join Date: Dec 2006
Posts: 474
Liked 17 Times on 13 Posts

Default

Why are you controlling the pumps with SSRs? Why not simple on/off switches like you have ahead of the SSRs? Also, I don't see any component like a PID controller that will control the SSRs for the elements. Finally, the BK will need a controller that throttles the power down so you can control the rate of boil, but the HLT needs a controller that runs to a temperature. I'm guessing you know this already, but had to be the smarty pants and ask.

__________________
AiredAle is offline
 
Reply With Quote Quick reply to this message
Old 03-29-2009, 10:15 PM   #9
HarvInSTL
Feedback Score: 0 reviews
 
HarvInSTL's Avatar
Recipes 
 
Join Date: Apr 2007
Location: Saint Louis, MO
Posts: 739
Liked 2 Times on 2 Posts
Likes Given: 1

Default

Quote:
Originally Posted by tipicreeper View Post
First off. Good luck with your build.
Next, you should add some down stream fusing to protect the wire gauge size and also the down stream componants.
For instance; appropiate sized fuses for each of your pumps and sized fuses for your heating elements. Essentially to protect against a catastophic failure. (a heating element was to burn out and fuse to ground or a pump winding was to fail) This will also allow you to drop wire gauge sizes in each of the branch circuits.
According to your diagram there is no branch fusing until the 50A breaker so the wire gauge size through out would be required to handle 50A before the jacket melts. That's some heavy gauge wire.
Also, I'm not seeing any controllers to control the SSR's. I would also fuse those with fast blow fuses.
Just my opinion,
If I can help in any way, please let me know.
Cheers
-David
Good point, I forget about fusing after the 50A breaker. I'll rework this diagram this evening and repost.

Quote:
Originally Posted by AiredAle View Post
Why are you controlling the pumps with SSRs? Why not simple on/off switches like you have ahead of the SSRs? Also, I don't see any component like a PID controller that will control the SSRs for the elements. Finally, the BK will need a controller that throttles the power down so you can control the rate of boil, but the HLT needs a controller that runs to a temperature. I'm guessing you know this already, but had to be the smarty pants and ask.
I won't be controlling the pumps. The BCS will be controlling the pumps via the SSR. I haven't added those to the diagram becuase I wanted to focus on the power aspect first.

I honestly don't need the SPST for the pumps. The DPST are so that I can break both legs to the elements. Compared to the SSR only breaking a single leg to the element. I want the ability to shut off all power to elements at any point, but truly those DPST switches will only be used twice a brew day.

The BCS will control the BK as well.
__________________
Primary: Cherry Vanilla Melomel, Blueberry melomel, Orange Cranberry Melomel, Port, Orange Blossom Muscat, Dubbel, Golden Strong

Secondary: 9/9/9/-My version, Carbernet Sauvignon, Merlot, Raspberry Melomel

On deck: Tripel, 5 day IPA Squared, White Russian Imperial Stout

Live in Saint Louis, MO? Then check out www.stlbrews.org and www.garagebrewers.com
HarvInSTL is offline
 
Reply With Quote Quick reply to this message
Old 03-30-2009, 01:58 AM   #10
IrishBeerBaron
Feedback Score: 0 reviews
Recipes 
 
Join Date: Jan 2009
Posts: 3
Default

Just this morning, I drew up pretty much this exact same diagram for my system ( including the BCS ).

I too had not fused downstream, but now plan to do so. Are you planning on using a bunch of fuse blocks or do inline fuse holders exist for the 30A lines? If so, anyone have an online source handy?

__________________
IrishBeerBaron is offline
 
Reply With Quote Quick reply to this message
Reply


Quick Reply
Message:
Options
Thread Tools


Similar Threads
Thread Thread Starter Forum Replies Last Post
Love Temp Controller Series TS wiring diagram (2008+) -TH- Equipment/Sanitation 91 03-27-2012 02:08 AM
Check my Wiring Diagram. Orangevango DIY Projects 16 08-16-2009 02:18 AM
Brewery Name - thoughts? Slipgate Label Display & Discussion 2 01-26-2009 01:58 PM
Elec. HERMS Wiring Diagram bmarley5780 DIY Projects 32 12-23-2008 02:05 PM
First thoughts about new (nano)brewery Cede DIY Projects 7 05-28-2007 10:46 PM