Default Estop wiring help with contractor brewtroller

This estop is pissing me off and I bought a contractor from ebrewsupply and can't figure how to wire it into my system. Can someone please help me figure this out? I basically need a dumby diagram. Anything would help. Thank you



image-4250439168.jpg



image-4265808293.jpg

__________________
kickflip_mj is offline
 
Reply With Quote Quick reply to this message
Old 12-02-2013, 03:07 AM   #2
heckels
Feedback Score: 0 reviews
Recipes 
 
Join Date: Jan 2011
Location: Sioux Falls, SD
Posts: 674
Liked 43 Times on 35 Posts

Default

Typically, that contactor would be used to cut power to the entire system which means it needs to be able to handle the entire load of the system. Are you sure that 25A is rated high enough to do so?

If you pass that test, I would hook it up as follows:
1. Use a common 120V neutral line.
2. Place the contactor inline between the "system power" indicator light and the control module.
3. Hook up your incoming 220V hot legs in line to that box on the far bottom right of your diagram.

*This assumes your estop button is NC and, is a twist style that remains open once pressed until twist reset.

__________________
heckels is offline
 
Reply With Quote Quick reply to this message
Old 12-02-2013, 06:08 AM   #3
kickflip_mj
Feedback Score: 0 reviews
Recipes 
 
Join Date: Jan 2008
Posts: 834
Liked 81 Times on 52 Posts
Likes Given: 3

Default

My system is gas fired and runs on 110. It wont draw that many amps.

__________________
kickflip_mj is offline
 
Reply With Quote Quick reply to this message
Old 12-02-2013, 08:17 PM   #4
kickflip_mj
Feedback Score: 0 reviews
Recipes 
 
Join Date: Jan 2008
Posts: 834
Liked 81 Times on 52 Posts
Likes Given: 3

Default

Thing thing is confusing as hell to me

__________________
kickflip_mj is offline
 
Reply With Quote Quick reply to this message
Old 12-02-2013, 08:55 PM   #5
jCOSbrew
HBT_SUPPORTER.png
Feedback Score: 0 reviews
Recipes 
 
Join Date: Feb 2012
Location: Colorado Springs, CO
Posts: 597
Liked 35 Times on 32 Posts
Likes Given: 7

Default

The estop switch should be in series with the contactor coil. If you have a control panel on/off switch it is also usually in series with the contactor coil. When the E-STOP AND the power switch are in the "ON" position the contactor will connect 110v (or 220v) power to the rest of your panel.

__________________
jCOSbrew is offline
 
Reply With Quote Quick reply to this message
Old 12-05-2013, 10:52 PM   #6
redbrewsathome
HBT_SUPPORTER.png
Feedback Score: 0 reviews
Recipes 
 
Join Date: Jan 2013
Location: Bayfield, Ontario
Posts: 22
Liked 1 Times on 1 Posts
Likes Given: 2

Default

Are you using the brewtroller e stop panel? If so that contactor only needs to kill the gas valves. The e stop board kills the coil on that contactor and your valves the brewtroller will then pause and wait for a restart. It does not need to kill the whole panel or you will lose your place in the brew program. My system is electric so I use two of those contactors to kill the elements the top two terminals are the coil and the bottom four are two separate circuits I use for both lines on my elements. It works pretty good!

__________________
redbrewsathome is online now
atoughram Likes This 
Reply With Quote Quick reply to this message
Old 12-06-2013, 12:10 AM   #7
atoughram
Feedback Score: 0 reviews
Recipes 
 
Join Date: May 2013
Location: Puyallup, Washington
Posts: 914
Liked 113 Times on 99 Posts
Likes Given: 169

Default

Quote:
Originally Posted by redbrewsathome View Post
Are you using the brewtroller e stop panel? If so that contactor only needs to kill the gas valves. The e stop board kills the coil on that contactor and your valves the brewtroller will then pause and wait for a restart. It does not need to kill the whole panel or you will lose your place in the brew program. My system is electric so I use two of those contactors to kill the elements the top two terminals are the coil and the bottom four are two separate circuits I use for both lines on my elements. It works pretty good!
This is the correct plan.... Just kill the gas valves and the pumps but leave the other electronics powered up.
__________________
Clover Creek Brewery, Puyallup WA
Planning - FS90 Amber Ale
Fermenters - Air
On tap
Ichter Hill IPA OG 1.058
Carbon River Hefe OG 1.049
atoughram is offline
 
Reply With Quote Quick reply to this message
Old 12-15-2013, 11:16 PM   #8
kickflip_mj
Feedback Score: 0 reviews
Recipes 
 
Join Date: Jan 2008
Posts: 834
Liked 81 Times on 52 Posts
Likes Given: 3

Default

Finally got it working, I was only running 12v through it like an amateur. Thank you guys for all the help

__________________
kickflip_mj is offline
andrhamm Likes This 
Reply With Quote Quick reply to this message
Reply


Quick Reply
Message:
Options
Thread Tools


Similar Threads
Thread Thread Starter Forum Replies Last Post
50 amp wiring diagram help - brewtroller gnatp2 Electric Brewing 29 10-31-2013 10:41 PM
Contractor not working. BWN Electric Brewing 35 03-26-2013 03:32 PM
Keezer Collar Temp Controller Wiring & Fan Wiring Questions. Revvy DIY Projects 12 09-23-2012 01:21 PM
Anyone have a 240v HERMS Brewtroller wiring diagram example? NinjaJoe Electric Brewing 2 02-27-2012 06:47 PM
Need help wiring 3 Position selector switch for Brewtroller EuBrew Electric Brewing 5 10-29-2010 04:39 PM