I just placed an order with Stout Tanks for a 1/2 barrel setup and I'm in the process of gathering all of the parts and pieces for a 50-amp PID back-to-back brewing system. I'll probably order a modified kit from ebrewsupply, get the Aubers PID's, timers, and deluxe RTD probes, and get a 16x16x8 steel enclosure from wherever.

I'm thinking two timers will be handy for back-to-back batches. I would like to have a separate alarm light for each PID and timer but have them all hooked up to one buzzer (if possible). That way I could tell which item is triggering the alarm. I think this would also be helpful for back-to-back batches as I may have an alarm going off for a timer at the same time an alarm is going off for reaching HLT temp (or whatever combo it may be).

Any input on this control panel layout is greatly appreciated!

File Type: pdf control panel.pdf (18.3 KB, 155 views)
__________________
cheez is offline
 
Reply With Quote Quick reply to this message
Old 01-25-2013, 05:34 PM   #2
LandoLincoln
HBT_SUPPORTER.png
Feedback Score: 0 reviews
 
LandoLincoln's Avatar
Recipes 
 
Join Date: Feb 2011
Location: Joliet, IL
Posts: 1,975
Liked 453 Times on 270 Posts
Likes Given: 11

Default

Quote:
Originally Posted by cheez View Post
Any input on this control panel layout is greatly appreciated!
Jeez, that's one heck of a logo plate.
__________________
LandoLincoln is offline
 
Reply With Quote Quick reply to this message
Old 01-25-2013, 05:51 PM   #3
cheez
HBT_SUPPORTER.png
Feedback Score: 0 reviews
 
cheez's Avatar
Recipes 
 
Join Date: Aug 2010
Location: Green Side of, WA
Posts: 182
Liked 6 Times on 6 Posts
Likes Given: 13

Default

Quote:
Originally Posted by LandoLincoln View Post
Jeez, that's one heck of a logo plate.
Smart a$$! Maybe I could put an LCD screen in there for beersmith or to watch a game while brewing
__________________
cheez is offline
 
Reply With Quote Quick reply to this message
Old 01-26-2013, 03:05 AM   #4
summerofgeorge
Feedback Score: 0 reviews
Recipes 
 
Join Date: Feb 2008
Location: Mount Laurel, NJ
Posts: 278
Liked 1 Times on 1 Posts

Default

Your panel is somewhat similar to mine. I was going to put the timers on each end. I thought it balanced the panel better.

Are you saying you'll have a light turn on when the alarm condition is met along with the shared buzzer? I hadn't thought of that. I was going to have small lights above each alarm switch to indicate that the alarm was active (small green lights in my panel). That way from a distance I could see which alarms were set. Now I'm wondering if I should bag those lights and do as you're saying or try to add another set of lights...

Here's a poor quality image of my panel. I'd post the actual in progress panel but it still needs a lot of work.

controlpanel50a.jpg  
__________________
summerofgeorge is offline
 
Reply With Quote Quick reply to this message
Old 01-26-2013, 05:47 AM   #5
cheez
HBT_SUPPORTER.png
Feedback Score: 0 reviews
 
cheez's Avatar
Recipes 
 
Join Date: Aug 2010
Location: Green Side of, WA
Posts: 182
Liked 6 Times on 6 Posts
Likes Given: 13

Default

Quote:
Originally Posted by summerofgeorge View Post
Your panel is somewhat similar to mine. I was going to put the timers on each end. I thought it balanced the panel better.

Are you saying you'll have a light turn on when the alarm condition is met along with the shared buzzer? I hadn't thought of that. I was going to have small lights above each alarm switch to indicate that the alarm was active (small green lights in my panel). That way from a distance I could see which alarms were set. Now I'm wondering if I should bag those lights and do as you're saying or try to add another set of lights...

Here's a poor quality image of my panel. I'd post the actual in progress panel but it still needs a lot of work.
I will have a red "alarm" light above each on/off alarm switch so I know what triggered the alarm and I'm hoping to have a shared alarm buzzer. I can easily see having a few alarms going off at the same time with back-to-back batches. I like your idea of having one timer at each end to balance it out.
__________________
cheez is offline
 
Reply With Quote Quick reply to this message
Old 01-26-2013, 09:08 PM   #6
cheez
HBT_SUPPORTER.png
Feedback Score: 0 reviews
 
cheez's Avatar
Recipes 
 
Join Date: Aug 2010
Location: Green Side of, WA
Posts: 182
Liked 6 Times on 6 Posts
Likes Given: 13

Default

Does anyone know if I will have any backfeeding issues if multiple alarms are going off at the same time and sending a signal to the single buzzer? I believe the Auber PID and timer outputs are NO so I don't think it will be a problem. Thanks.

__________________
cheez is offline
 
Reply With Quote Quick reply to this message
Old 01-29-2013, 12:23 AM   #7
cheez
HBT_SUPPORTER.png
Feedback Score: 0 reviews
 
cheez's Avatar
Recipes 
 
Join Date: Aug 2010
Location: Green Side of, WA
Posts: 182
Liked 6 Times on 6 Posts
Likes Given: 13

Default

Quote:
Originally Posted by cheez View Post
Does anyone know if I will have any backfeeding issues if multiple alarms are going off at the same time and sending a signal to the single buzzer? I believe the Auber PID and timer outputs are NO so I don't think it will be a problem. Thanks.
Any input on this? I'm hoping to start ordering control panel parts this week. Thanks for any help.
__________________
cheez is offline
 
Reply With Quote Quick reply to this message
Old 01-30-2013, 01:42 PM   #8
BadNewsBrewery
Basement Brewer
HBT_SUPPORTER.png
Feedback Score: 0 reviews
 
BadNewsBrewery's Avatar
Recipes 
 
Join Date: Oct 2012
Location: Severn, MD
Posts: 1,067
Liked 108 Times on 89 Posts
Likes Given: 36

Default

First, the answer to your question - I have been told there are no issues with backfeed, so you should be good (depending on how you wire it up, you may have your lights get backfed, but it can be avoided).

Now, some comments. It's your panel, so do what you want with the comments...
1 - You can save yourself a lot of extra holes and wiring if you use light up switches. Eliminate almost all of your lights - push the button, it lights up - two jobs, one switch. If you were set on having the alarm lights, you could even incorporate them into switches so they light up whenever your conditions are met.

2 - If the alarm light is only there to let you know which of the PIDs / Timers is sending the signal to the alarm buzzer, you may not need it. The PIDs will have an LED on them to indicate which is in alarm. Not sure about the timers. It won't be as bright or obvious as the separate light, but it should be pretty easy to figure out which device is in alarm based on the integrated alarm LED.

3 - I agree with the idea of having the timers on either side for a more balanced look, but that's up to you.

4 - Are you going to be able to shoehorn 5 PIDs into the box? I have 3, and it's tight but not terrible. I could see 4, but 5 would be a beast. Also, you can't get too close to the lock-side of the panel, as the PIDs have some decent dept to them and they will hit as you open the door. Keep in mind that you lose about an inch on all sides for the weather gasket and lip on the box.

Hope those help...
-Kevin

__________________
Building a Bad News Brewery - eHERMS

2014:
5gal Scottish Wee Heavy
5gal Saison
15gal American Pale Ale
20gal Belgian Wit (10 dumped)


Keg 1: Apfelwein
Keg 2: Belgian Wit (Failure)
Keg 3: American Pale Ale
Fermenting: Belgian Wit (Take 2)
BadNewsBrewery is offline
mikescooling Likes This 
Reply With Quote Quick reply to this message
Old 01-30-2013, 03:23 PM   #9
cheez
HBT_SUPPORTER.png
Feedback Score: 0 reviews
 
cheez's Avatar
Recipes 
 
Join Date: Aug 2010
Location: Green Side of, WA
Posts: 182
Liked 6 Times on 6 Posts
Likes Given: 13

Default

Quote:
Originally Posted by BadNewsBrewery View Post
First, the answer to your question - I have been told there are no issues with backfeed, so you should be good (depending on how you wire it up, you may have your lights get backfed, but it can be avoided).

Now, some comments. It's your panel, so do what you want with the comments...
1 - You can save yourself a lot of extra holes and wiring if you use light up switches. Eliminate almost all of your lights - push the button, it lights up - two jobs, one switch. If you were set on having the alarm lights, you could even incorporate them into switches so they light up whenever your conditions are met.

2 - If the alarm light is only there to let you know which of the PIDs / Timers is sending the signal to the alarm buzzer, you may not need it. The PIDs will have an LED on them to indicate which is in alarm. Not sure about the timers. It won't be as bright or obvious as the separate light, but it should be pretty easy to figure out which device is in alarm based on the integrated alarm LED.

3 - I agree with the idea of having the timers on either side for a more balanced look, but that's up to you.

4 - Are you going to be able to shoehorn 5 PIDs into the box? I have 3, and it's tight but not terrible. I could see 4, but 5 would be a beast. Also, you can't get too close to the lock-side of the panel, as the PIDs have some decent dept to them and they will hit as you open the door. Keep in mind that you lose about an inch on all sides for the weather gasket and lip on the box.

Hope those help...
-Kevin
Thanks for your input! I've been following your build thread - great work!

For some reason I like the look of the separate LED indicator lights and switches but I may use the push button lighted switches for the alarm switches/lights as they would eliminate 5 holes. I believe the Aubers timers have an "out" indicator light that lights up for the alarm.

Based on my current conceptual layout, I have about a 1.5" space between the outside of the box and the PID's, switches, etc. and have a 1" space between the PID's/Alarms. I thought about going with a 20"x16" or 20"x20" enclosure but they are harder to find and seem to cost a lot more than 16"x16".

Thanks again for your input.

Chris
__________________
cheez is offline
 
Reply With Quote Quick reply to this message
Old 02-17-2013, 04:24 AM   #10
cheez
HBT_SUPPORTER.png
Feedback Score: 0 reviews
 
cheez's Avatar
Recipes 
 
Join Date: Aug 2010
Location: Green Side of, WA
Posts: 182
Liked 6 Times on 6 Posts
Likes Given: 13

Default

Any more input on this? I should be getting my Stout tanks order in April and would like to get a jump start on the control panel build. My concern at this point is that there may not be enough room on a 16x16 panel for all of the gear I want. Any thoughts? I know a 16x20 would work but they seem to be a lot harder to find and a lot more expensive. Thanks!

File Type: pdf control panel 2.pdf (18.2 KB, 24 views)
__________________
cheez is offline
 
Reply With Quote Quick reply to this message
Reply


Quick Reply
Message:
Options
Thread Tools


Similar Threads
Thread Thread Starter Forum Replies Last Post
Requesting help with 220V control panel design makubex Electric Brewing 4 01-26-2013 02:46 AM
Looking for input on my control panel wiring diagram bberr004 Electric Brewing 4 09-11-2012 10:26 PM
Control panel layout critique/ideas summerofgeorge Electric Brewing 11 03-25-2012 02:25 AM
Control Panel Layout/Labels Bobby_M Electric Brewing 6 11-17-2011 01:53 PM
need input on control panel SpaceCoastBrew Electric Brewing 13 10-28-2010 02:28 PM